Lesson 3 of 3 · 9 min
Work in progress: over and under billing
Compare what you've billed with what you've earned, job by job.
Beta: accounting review in progress
Under ASC 606, revenue on most construction contracts is recognized over time as the work progresses, often measured by cost to date ÷ total estimated cost (the cost-to-cost method). What you've billed can be ahead of that or behind it.
Example. Contract $500,000, estimated cost $400,000. Cost to date $200,000, so 50% complete and $250,000 earned. Billed $280,000: over billed by $30,000, a liability (you've billed for work not yet done).
- Over billing: billed more than earned. Shown as a liability (contract liability). Healthy in moderation; large over billings can hide trouble.
- Under billing: earned more than billed. Shown as an asset (contract asset). Can mean slow billing, unapproved change orders or a job going over cost.
Bonding companies and lenders read the WIP schedule closely, and fade (profit shrinking as a job goes) is the first thing they look for.
In AccLyf Books. Reports → WIP builds the schedule from job estimates and the books, posting nothing. Posting the over/under adjustment is the owner's choice (Settings, construction).
Check what you learned
This lesson has a 3-question quiz, and the course ends with a task you do in a demo company while the app checks your work. Both come free with an account.
Take the quiz with a free accountStandards behind this lesson
- FASB ASC Topic 606, Revenue from Contracts with Customers (cited by number; not quoted)
- FASB ASC Topic 910, Contractors: Construction (cited by number; not quoted)
- FASB ASC Topic 340, Other Assets and Deferred Costs (cited by number; not quoted)
Cited for further reading. Standards are named, not quoted; the lesson is our own explanation.
General education about bookkeeping and using AccLyf Books. It isn't accounting, tax or legal advice for your situation; for that, talk to a CPA, tax professional or attorney.